MISO-J2116
18 MW generation in Cook, MN · In queue since December 2023 · Proposed COD September 2022
18 MW
Capacity
1
Components
Diesel
2y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
2y 5m
Schedule
45 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-09-01
MISO-J2116 is a proposed 18 MW diesel generation project located in Cook County, Minnesota. The project, under development by Great River Energy, entered the MISO interconnection queue on December 8, 2023, with a proposed commercial operation date of September 1, 2022. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The project consists of 18 MW of diesel generation capacity. It is interconnected to the grid at the Colvill point of interconnection. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
MN
County
Cook
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
GREAT RIVER ENERGY
Entity
MISO
Service Type
—
Point of Interconnection
Colvill
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2116