MISO-J2122
33 MW generation in Franklin, IA · In queue since August 2021 · Proposed COD June 2024
33 MW
Capacity
1
Components
Wind
4y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
2y 10m
Schedule
22 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-06-30
MISO-J2122 is a proposed 33 MW wind generation project located in Franklin County, Iowa. The project, which interconnects with ITC Midwest at the Nuthatch Switching Substation, entered the MISO interconnection queue on August 4, 2021. Its proposed commercial operation date is June 30, 2024.
The interconnection agreement for MISO-J2122 is currently listed as "In Progress (unknown study)". The project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
IA
County
Franklin
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC MIDWEST
Entity
MISO
Service Type
—
Point of Interconnection
Nuthatch Switching Substation
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2122