MISO-J2124
100 MW storage in Champaign, IL · In queue since August 2021 · Proposed COD December 2022
100 MW
Capacity
1
Components
Battery
4y 9m
In Queue
Cluster Study
IA Status
COD target: 2022
Total Duration
1y 4m
Schedule
42 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-02
MISO-J2124 is a proposed 100 MW battery storage project located in Champaign County, Illinois. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of August 6, 2021. The proposed commercial operation date is December 2, 2022. The interconnection status is currently in the Cluster Study phase.
The project, which is being developed within the Ameren Transmission Company of Illinois service area, consists of 100 MW of battery storage capacity. The point of interconnection (POI) is at the Rising substation. The project is currently listed as active in the MISO queue.
Generated from interconnection queue and public data sources
State
IL
County
Champaign
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN TRANSMISSION COMPANY OF ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Rising
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Rising Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2124