MISO-J2128
300 MW hybrid in Coles, IL · In queue since August 2021 · Proposed COD August 2024
300 MW
Capacity
1
Components
Wind
4y 9m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
3 years
Schedule
20 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-08-31
The proposed MISO-J2128 project is a 300 MW hybrid wind and battery energy storage development project located in Coles County, Illinois. Interconnection to the Ameren Illinois system is planned at the Farady to Kansas 345 kV point of interconnection.
The project is in the MISO interconnection queue with an entry date of August 13, 2021, and a proposed commercial operation date of August 31, 2024. The project's interconnection status is currently in the Cluster Study phase. News coverage of the project has appeared in recent news.
Generated from interconnection queue and public data sources
State
IL
County
Coles
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Farady to Kansas 345 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2128