Project MISO-J2129 — Project Summary

Queue ID
MISO-J2129
Capacity
150 MW
Technology
Solar+Battery
Status
active
Location
Barry, MI
Region
MISO
Developer
IA Status
Cluster Study

MISO-J2129

MISO-J2129BetaActiveSolarBatteryMISOLBNL + Live

150 MW hybrid in Barry, MI · In queue since August 2021 · Proposed COD April 2024

150 MW

Capacity

1

Components

Solar

4y 9m

In Queue

Cluster Study

IA Status

COD target: 2024

Interconnection

Total Duration

2y 8m

Schedule

25 months past proposed COD

Impact Study25%
Queue EntryAug 26, 2021

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-04-15

About

MISO-J2129 is a proposed 150 MW hybrid solar and battery project located in Barry County, Michigan. The project, which consists of 150 MW of solar generation, is in the Midcontinent Independent System Operator (MISO) interconnection queue. Wolverine Power Supply Cooperative is the listed utility.

The project entered the MISO queue on August 26, 2021, with a proposed commercial operation date of April 15, 2024. Its interconnection status is currently listed as "Cluster Study". The point of interconnection is the Bradley 138 kV Substation.

Generated from interconnection queue and public data sources

Project Details

State

MI

County

Barry

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

WOLVERINE POWER SUPPLY COOPERATIVE

Entity

MISO

Service Type

Point of Interconnection

Bradley 138 kV Substation

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
MISO
Trading Hub
MICHIGAN.HUB
Hub Confidence
HIGH
POI Substation
Bradley Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.