MISO-J2129
150 MW hybrid in Barry, MI · In queue since August 2021 · Proposed COD April 2024
150 MW
Capacity
1
Components
Solar
4y 9m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
2y 8m
Schedule
25 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-04-15
MISO-J2129 is a proposed 150 MW hybrid solar and battery project located in Barry County, Michigan. The project, which consists of 150 MW of solar generation, is in the Midcontinent Independent System Operator (MISO) interconnection queue. Wolverine Power Supply Cooperative is the listed utility.
The project entered the MISO queue on August 26, 2021, with a proposed commercial operation date of April 15, 2024. Its interconnection status is currently listed as "Cluster Study". The point of interconnection is the Bradley 138 kV Substation.
Generated from interconnection queue and public data sources
State
MI
County
Barry
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
WOLVERINE POWER SUPPLY COOPERATIVE
Entity
MISO
Service Type
—
Point of Interconnection
Bradley 138 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Bradley Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2129