MISO-J2136
190.9 MW generation in Iroquois, IL · In queue since March 2022 · Proposed COD September 2024
190.9 MW
Capacity
1
Components
Solar
4y 2m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
2y 6m
Schedule
20 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-01
The proposed MISO-J2136 project is a 190.9 MW solar generation project located in Iroquois County, Illinois. Interconnection is with Ameren Illinois via the Gilman substation at 138 kV. The project entered the MISO interconnection queue on March 23, 2022, with a proposed commercial operation date of September 1, 2024. Its interconnection status is currently in the Cluster Study phase.
The development project consists solely of solar generation, with a total capacity of 190.9 MW.
Generated from interconnection queue and public data sources
State
IL
County
Iroquois
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Gilman substation 138 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Gilman Substation