MISO-J2142
150 MW hybrid in Adair, MO · In queue since November 2021 · Proposed COD August 2024
150 MW
Capacity
1
Components
Solar
4y 6m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
2y 9m
Schedule
21 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-08-01
MISO-J2142 is a proposed 150 MW hybrid solar and battery project located in Adair County, Missouri. The project, which consists of 150 MW of solar generation, is in the Midcontinent Independent System Operator (MISO) interconnection queue. Its queue entry date is November 3, 2021, and the proposed commercial operation date is August 1, 2024. Ameren Missouri is the utility associated with the project.
The project's interconnection status is currently in the Cluster Study phase. The point of interconnection (POI) is the Maywood - Zachary 345 kV line. The project has appeared in recent news coverage regarding renewable energy development in the MISO region.
Generated from interconnection queue and public data sources
State
MO
County
Adair
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN MISSOURI
Entity
MISO
Service Type
—
Point of Interconnection
Maywood - Zachary 345 kV line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.