MISO-J2151
150 MW hybrid in Saline, IL · In queue since August 2021 · Proposed COD August 2025
150 MW
Capacity
1
Components
Solar
4y 9m
In Queue
Cluster Study
IA Status
COD target: 2025
Total Duration
4 years
Schedule
9 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-08-01
MISO-J2151 is a proposed 150 MW hybrid solar and battery project located in Saline County, Illinois. The project, which consists of 150 MW of solar generation, is in the MISO interconnection queue as of August 12, 2021. The proposed commercial operation date is August 1, 2025.
The interconnection point of contact is the Muddy to West Frankfort 138 kV line. The project's interconnection status is currently in the Cluster Study phase. The utility involved is Ameren Illinois.
Generated from interconnection queue and public data sources
State
IL
County
Saline
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Muddy to West Frankfort 138 kV line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Muddy