MISO-J2155
150 MW generation in New Madrid, MO · In queue since March 2022 · Proposed COD May 2024
150 MW
Capacity
1
Components
Solar
4y 2m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
2y 2m
Schedule
23 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-05-31
The proposed MISO-J2155 project is a 150 MW solar generation facility located in New Madrid County, Missouri. The project, under consideration by Ameren Missouri, entered the MISO interconnection queue on March 28, 2022, with a proposed commercial operation date of May 31, 2024. Its interconnection status is currently in the Cluster Study phase.
The point of interconnection (POI) for the project is the Reelfoot - Sikeston 161 kV Line, associated with MTEP Project 19852 and Facility ID 26201.
Generated from interconnection queue and public data sources
State
MO
County
New Madrid
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN MISSOURI
Entity
MISO
Service Type
—
Point of Interconnection
Reelfoot - Sikeston 161 kV Line MTEP Project 19852 Facility ID 26201
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2155