MISO-J2170
150 MW storage in Clark, IL · In queue since April 2022 · Proposed COD January 2024
150 MW
Capacity
1
Components
Battery
4y 1m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
1y 9m
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-01-01
MISO-J2170 is a proposed 150 MW battery storage project located in Clark County, Illinois. The project, which is in the Ameren Illinois service area, entered the MISO interconnection queue on April 5, 2022, with a proposed commercial operation date of January 1, 2024. Its interconnection status is currently in the Cluster Study phase.
The development project consists of a 150 MW battery energy storage system. The point of interconnection is at the Snyder 345 kV substation, specifically the J1180/J1475 POI.
Generated from interconnection queue and public data sources
State
IL
County
Clark
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Snyder 345 kV (J1180/J1475 POI)
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2170