MISO-J2171
500 MW hybrid in Perry, IL · In queue since March 2022 · Proposed COD May 2024
500 MW
Capacity
1
Components
Solar
4y 2m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
2y 2m
Schedule
24 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-05-01
MISO-J2171 is a proposed 500 MW hybrid solar and wind project located in Perry County, Illinois. The project consists of 500 MW of solar generation. It is listed in the MISO interconnection queue as of March 25, 2022, with a proposed commercial operation date of May 1, 2024. The interconnection point of contact is Aster to Commodore. Its interconnection status is currently in the Cluster Study phase.
The project is in the Ameren Illinois utility service area. It is listed as an active project in the MISO queue.
Generated from interconnection queue and public data sources
State
IL
County
Perry
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Aster to Commodore
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.