MISO-J2177
67 MW generation in Tipton, IN · In queue since August 2021 · Proposed COD October 2024
67 MW
Capacity
1
Components
Solar
4y 9m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
3y 2m
Schedule
18 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-10-30
MISO-J2177 is a proposed solar generation project located in Tipton County, Indiana, within the Midcontinent Independent System Operator (MISO) region. The project, with a total capacity of 67 MW, consists entirely of solar photovoltaic technology. Duke Energy Indiana is the utility associated with the interconnection.
The project entered the MISO interconnection queue on August 9, 2021, and has a proposed commercial operation date of October 30, 2024. Its interconnection status is currently in the Cluster Study phase, and the point of interconnection is the Tipton West 230 kV substation.
Generated from interconnection queue and public data sources
State
IN
County
Tipton
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
DUKE ENERGY INDIANA
Entity
MISO
Service Type
—
Point of Interconnection
Tipton West 230 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- HIGH
- POI Substation
- Tipton West Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.