MISO-J2178
100 MW storage in Sullivan, IN · In queue since August 2021 · Proposed COD October 2024
100 MW
Capacity
1
Components
Battery
4y 9m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
3y 2m
Schedule
18 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-10-30
MISO-J2178 is a proposed 100 MW battery storage project located in Sullivan County, Indiana. The project, developed by Hoosier Energy, is interconnected within the Midcontinent Independent System Operator (MISO) region. It entered the MISO interconnection queue on August 6, 2021, with a proposed commercial operation date of October 30, 2024. The project's interconnection status is currently in the Cluster Study phase.
The development project consists solely of battery storage, with a total capacity of 100 MW. The point of interconnection (POI) is at the Merom 345 kV substation. The project is currently listed as active within the MISO queue.
Generated from interconnection queue and public data sources
State
IN
County
Sullivan
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
HOOSIER ENERGY
Entity
MISO
Service Type
—
Point of Interconnection
Merom 345 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- HE.MEROM2
- POI Substation
- Merom Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2178