MISO-J2186
820.6 MW generation in Fulton, IL · In queue since June 2022 · Proposed COD October 2024
820.6 MW
Capacity
1
Components
Solar
3y 11m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
2y 4m
Schedule
19 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-10-01
MISO-J2186 is a proposed solar generation project with a total capacity of 820.6 MW. The project is located in Fulton County, Illinois, within the Midcontinent Independent System Operator (MISO) region and is being developed within the Ameren Illinois utility territory. The project entered the MISO interconnection queue on June 22, 2022, with a proposed commercial operation date of October 1, 2024.
The interconnection status of MISO-J2186 is currently in the Cluster Study phase. The point of interconnection (POI) for the project is the Ipava-Maple Ridge 345kV substation (4573).
Generated from interconnection queue and public data sources
State
IL
County
Fulton
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Ipava-Maple Ridge 345kV (4573)
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.