MISO-J2187
124 MW generation in Laporte, IN · In queue since March 2022 · Proposed COD October 2024
124 MW
Capacity
1
Components
Solar
4y 2m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
2y 7m
Schedule
19 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-10-20
MISO-J2187 is a proposed solar generation project with a total capacity of 124 MW. The project is located in Laporte County, Indiana, and is interconnected within the Midcontinent Independent System Operator (MISO) region. The queue entry date for MISO-J2187 is March 28, 2022, with a proposed commercial operation date of October 20, 2024. The project's interconnection status is currently in the Cluster Study phase.
The proposed project is being developed within the Northern Indiana Public Service Company (NIPSCO) utility territory.
Generated from interconnection queue and public data sources
State
IN
County
Laporte
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
NORTHERN INDIANA PUBLIC SERVICE COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Stillwell 138kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- HIGH
- POI Substation
- Stillwell Substation