MISO-J2193
100 MW hybrid in Waushara, WI · In queue since November 2021 · Proposed COD September 2024
100 MW
Capacity
1
Components
Solar
4y 6m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
2y 10m
Schedule
20 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-01
The proposed MISO-J2193 project is a 100 MW hybrid solar and battery energy storage development project located in Waushara County, Wisconsin. The project consists of 100 MW of solar generation. It is interconnected within the Midcontinent Independent System Operator (MISO) region, and is in the American Transmission Company service area.
The project entered the MISO interconnection queue on November 30, 2021, with a proposed commercial operation date of September 1, 2024. Its interconnection status is currently in the Cluster Study phase. The point of interconnection is the Sand Lake 138kV Substation.
Generated from interconnection queue and public data sources
State
WI
County
Waushara
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Sand Lake 138kV Substation
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Sand Lake
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2193