MISO-J2195
100 MW storage in Fayette, IL · In queue since March 2022 · Proposed COD October 2024
100 MW
Capacity
1
Components
Battery
4y 2m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
2y 7m
Schedule
19 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-10-07
MISO-J2195 is a proposed 100 MW battery storage project located in Fayette County, Illinois. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered on March 24, 2022. The proposed commercial operation date is October 7, 2024. Ameren Illinois is the utility associated with the project, which is currently in the Cluster Study phase of the interconnection process.
The point of interconnection (POI) for the development project is the Ramsey East 138 kV substation. The project consists solely of battery storage, with a total capacity of 100 MW.
Generated from interconnection queue and public data sources
State
IL
County
Fayette
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Ramsey East 138 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Ramsey
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2195