MISO-J2197
100 MW storage in Clay, IL · In queue since March 2022 · Proposed COD October 2024
100 MW
Capacity
1
Components
Battery
4y 2m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
2y 7m
Schedule
19 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-10-07
MISO-J2197 is a proposed 100 MW battery storage project located in Clay County, Illinois. The project, which consists entirely of battery storage, is interconnected within the Midcontinent Independent System Operator (MISO) region, with Ameren Illinois as the utility.
The project entered the MISO interconnection queue on March 25, 2022, and has a proposed commercial operation date of October 7, 2024. Its interconnection status is currently in the Cluster Study phase, and the point of interconnection is the Xenia 345 kV substation.
Generated from interconnection queue and public data sources
State
IL
County
Clay
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Xenia 345 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2197