MISO-J2205
300 MW hybrid in Callaway, MO · In queue since August 2021 · Proposed COD September 2024
300 MW
Capacity
1
Components
Solar
4y 9m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
3y 1m
Schedule
20 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-01
The proposed MISO-J2205 project is a 300 MW solar and battery hybrid development in Callaway County, Missouri. Interconnecting within the Midcontinent Independent System Operator (MISO) region, the project entered the queue on August 12, 2021, with a proposed commercial operation date of September 1, 2024. The project, which is being developed within the Ameren Missouri service area, consists of 300 MW of solar generation capacity.
The interconnection request is currently in the Cluster Study phase. The point of interconnection (POI) is the J1145 New 345kV POI Substation on the Ameren Overton-Montgomery 345kV Line.
Generated from interconnection queue and public data sources
State
MO
County
Callaway
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN MISSOURI
Entity
MISO
Service Type
—
Point of Interconnection
J1145 New 345kV POI Substation (Ameren Overton-Montgomery 345kV Line)
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2205