MISO-J2215
300 MW storage in Lake, IN · In queue since March 2022 · Proposed COD September 2024
300 MW
Capacity
1
Components
Battery
4y 2m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
2y 6m
Schedule
19 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-30
MISO-J2215 is a proposed 300 MW battery storage project located in Lake County, Indiana. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of March 25, 2022. The proposed commercial operation date is September 30, 2024. The interconnecting utility is Northern Indiana Public Service Company.
The project's interconnection status is currently in the Cluster Study phase. The point of interconnection (POI) is the Schahfer Generating Station - St. John 345.0kV.
Generated from interconnection queue and public data sources
State
IN
County
Lake
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
NORTHERN INDIANA PUBLIC SERVICE COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
SCHAHFER GEN STA - ST. JOHN 345.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2215