Project MISO-J2227 — Project Summary

Queue ID
MISO-J2227
Capacity
89 MW
Technology
Solar
Status
active
Location
Trempealeau, WI
Region
MISO
Developer
IA Status
In Progress (unknown study)

MISO-J2227

MISO-J2227BetaActiveSolarMISOLBNL + Live

89 MW generation in Trempealeau, WI · In queue since November 2021 · Proposed COD October 2024

89 MW

Capacity

1

Components

Solar

4y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection

Total Duration

2y 11m

Schedule

18 months past proposed COD

In Study38%
Queue EntryNov 30, 2021

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-10-31

About

MISO-J2227 is a proposed solar generation project with a total capacity of 89 MW. The project is located in Trempealeau County, Wisconsin, and is being developed within the Midcontinent Independent System Operator (MISO) region. The queue entry date for the project is November 30, 2021, with a proposed commercial operation date of October 31, 2024. The interconnecting utility is Dairyland Power Cooperative.

The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the N-3 Bridge Creek to Independence 69kV Line.

Generated from interconnection queue and public data sources

Project Details

State

WI

County

Trempealeau

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

DAIRYLAND POWER COOPERATIVE

Entity

MISO

Service Type

Point of Interconnection

N-3 Bridge Creek to Independence 69kV Line [See Operating Agreement 5 for Correction Discussion]

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
MISO
Trading Hub
MINN.HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.