MISO-J2233
100 MW generation in Vermilion, IL · In queue since June 2022 · Proposed COD August 2024
100 MW
Capacity
1
Components
Solar
3y 11m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
2y 2m
Schedule
21 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-08-01
The proposed MISO-J2233 project is a 100 MW solar generation facility located in Vermilion County, Illinois. The project, which is in the Ameren Illinois service area, entered the MISO interconnection queue on June 14, 2022, with a proposed commercial operation date of August 1, 2024. Its interconnection status is currently in the Cluster Study phase.
The project consists of 100 MW of solar photovoltaic generation. The point of interconnection is the Sidney - Bunsonville 345kV line.
Generated from interconnection queue and public data sources
State
IL
County
Vermilion
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Sidney - Bunsonville 345kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2233