MISO-J2247
178 MW generation in Marshall, IL · In queue since March 2022 · Proposed COD September 2024
178 MW
Capacity
1
Components
Wind
4y 2m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
2y 6m
Schedule
20 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-01
MISO-J2247 is a proposed wind generation project with a total capacity of 178 MW, located in Marshall County, Illinois. The project is in the MISO interconnection queue, having entered on March 25, 2022, with a proposed commercial operation date of September 1, 2024. The interconnecting utility is Ameren Illinois. Its interconnection status is currently in the Cluster Study phase.
The development project consists solely of wind generation, with 178 MW of wind capacity. The point of interconnection (POI) is Woodhall.
Generated from interconnection queue and public data sources
State
IL
County
Marshall
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Woodhall
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2247