MISO-J2250
200 MW generation in Stutsman, ND · In queue since November 2021 · Proposed COD April 2024
200 MW
Capacity
1
Components
Wind
4y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
2y 5m
Schedule
25 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-04-01
MISO-J2250 is a proposed 200 MW wind generation project located in Stutsman County, North Dakota. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of November 1, 2021, and a proposed commercial operation date of April 1, 2024. The designated point of interconnection (POI) is the Ellendale substation at 345 kV.
The project's interconnection agreement (IA) status is listed as "In Progress (unknown study)". Montana-Dakota Utilities Co. is the utility associated with the project. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
ND
County
Stutsman
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
MONTANA-DAKOTA UTILITIES CO.
Entity
MISO
Service Type
—
Point of Interconnection
Ellendale sub 345 kV (46.009357, -98.567742)
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2250