MISO-J2265
200 MW hybrid in Bollinger, MO · In queue since September 2021 · Proposed COD February 2024
200 MW
Capacity
1
Components
Solar
4y 8m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
2y 5m
Schedule
27 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-02-15
MISO-J2265 is a proposed 200 MW hybrid solar and battery project located in Bollinger County, Missouri. The development project, with Ameren Missouri as the utility, entered the MISO interconnection queue on September 7, 2021. The proposed commercial operation date is February 15, 2024.
The project's interconnection status is currently in the Cluster Study phase. The point of interconnection is the St. Francois (Bus #345773) - Lutesville (Bus #344974) 345 kV Line. The solar component has a capacity of 200 MW.
Generated from interconnection queue and public data sources
State
MO
County
Bollinger
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN MISSOURI
Entity
MISO
Service Type
—
Point of Interconnection
St. Francois (Bus #345773) - Lutesville (Bus #344974) 345 kV Line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2265