MISO-J2266
175 MW hybrid in Edgar, IL · In queue since March 2022 · Proposed COD March 2025
175 MW
Capacity
1
Components
Solar
4y 2m
In Queue
Cluster Study
IA Status
COD target: 2025
Total Duration
3 years
Schedule
13 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-03-31
MISO-J2266 is a proposed 175 MW hybrid solar and battery energy storage project located in Edgar County, Illinois. The project, which consists of 175 MW of solar generation, is in the MISO interconnection queue as of March 24, 2022, with a proposed commercial operation date of March 31, 2025. The interconnection point is the Kansas (endpoint A) - Sugar Creek (endpoint B) 345 kV line.
The project's interconnection status is currently in the Cluster Study phase. The utility involved is Ameren Illinois.
Generated from interconnection queue and public data sources
State
IL
County
Edgar
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Kansas (endpoint A) - Sugar Creek (endpoint B) 345 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2266