MISO-J2268
400 MW generation in Linn, IA · In queue since August 2021 · Proposed COD October 2024
400 MW
Capacity
1
Components
Solar
4y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 2m
Schedule
18 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-10-30
MISO-J2268 is a proposed solar generation project with a total capacity of 400 MW, located in Linn County, Iowa. The project is interconnected within the Midcontinent Independent System Operator (MISO) queue, having entered the queue on August 11, 2021. Its proposed commercial operation date is October 30, 2024. The interconnection agreement status is listed as "In Progress (unknown study)".
The point of interconnection (POI) for MISO-J2268 is the Duane Arnold Energy Center. The project is listed as active in the MISO interconnection queue. The transmission utility is ITC Midwest.
Generated from interconnection queue and public data sources
State
IA
County
Linn
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC MIDWEST
Entity
MISO
Service Type
—
Point of Interconnection
Duane Arnold Energy Center
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- ALTE.BVRDAM
- POI Substation
- Center St
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.