MISO-J2272
250 MW hybrid in Clinton, IA · In queue since July 2021 · Proposed COD September 2024
250 MW
Capacity
1
Components
Solar
4y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 2m
Schedule
20 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-01
MISO-J2272 is a proposed 250 MW hybrid solar and battery project located in Clinton County, Iowa. The project consists of 250 MW of solar generation. It is interconnected within the Midcontinent Independent System Operator (MISO) queue as of July 22, 2021, with a proposed commercial operation date of September 1, 2024. The project's interconnection agreement status is listed as "In Progress (unknown study)" and the point of interconnection is the 161kV East Calamus Substation, served by ITC Midwest.
The development project is listed in the MISO interconnection queue under queue ID MISO-J2272.
Generated from interconnection queue and public data sources
State
IA
County
Clinton
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC MIDWEST
Entity
MISO
Service Type
—
Point of Interconnection
161kV East Calamus Substation
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Calamus East Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.