MISO-J2273
175 MW hybrid in Clinton, IL · In queue since March 2022 · Proposed COD March 2024
175 MW
Capacity
1
Components
Solar
4y 2m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
2 years
Schedule
25 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-03-31
MISO-J2273 is a proposed 175 MW hybrid solar and battery project located in Clinton County, Illinois. The project, which consists of 175 MW of solar generation, is in the MISO interconnection queue as of March 24, 2022, with a proposed commercial operation date of March 31, 2024. The interconnection point of the project is the Tabor 138kV Substation, and its interconnection status is currently in the Cluster Study phase.
The development project is located within the Ameren Illinois utility service area. It is listed as an active project in the MISO queue.
Generated from interconnection queue and public data sources
State
IL
County
Clinton
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Tabor 138kV Substation
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Tabor Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2273