MISO-J2276
39.5 MW hybrid in Douglas, MN · In queue since April 2022 · Proposed COD January 2022
39.5 MW
Capacity
1
Components
Solar
4y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
4y 1m
Schedule
53 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-01-01
MISO-J2276 is a proposed hybrid solar and wind project with a total capacity of 39.5 MW. The project, located in Douglas County, Minnesota, is interconnected within the Midcontinent Independent System Operator (MISO) queue. The queue entry date is April 11, 2022, with a proposed commercial operation date of January 1, 2022. The interconnection agreement status is listed as "In Progress (unknown study)".
The project is composed of 39.5 MW of solar generation. The interconnecting utility is Missouri River Energy Services - Transmission. The project is currently listed as active in the MISO interconnection queue.
Generated from interconnection queue and public data sources
State
MN
County
Douglas
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
MISSOURI RIVER ENERGY SERVICES - TRANSMISSION
Entity
MISO
Service Type
—
Point of Interconnection
ALEXANDRIA
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- MRES Alexandria Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2276