MISO-J230
70 MW generation in MI · In queue since September 2011 · Proposed COD May 2018
70 MW
Capacity
1
Components
Hydro
14y 8m
In Queue
IA Executed
IA Status
COD target: 2018
Total Duration
6y 8m
Schedule
97 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–36 months
Proposed COD: 2018-05-25
MISO-J230 is a proposed 70 MW hydroelectric generation project located in Michigan within the Midcontinent Independent System Operator (MISO) region. The project, consisting of 70 MW of hydro capacity, entered the MISO interconnection queue on September 27, 2011, with a proposed commercial operation date of May 25, 2018. The interconnection agreement (IA) for the project has been executed. The point of interconnection is the Ludington Substation.
The project is currently listed as active in the MISO queue.
Generated from interconnection queue and public data sources
State
MI
County
—
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
—
Point of Interconnection
Ludington Substation
Data Source
LBNL
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- DECO.LUD1
- POI Substation
- Ludington Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J230