MISO-J2311
145 MW generation in Lasalle, IL · In queue since October 2024 · Proposed COD February 2024
145 MW
Capacity
1
Components
Wind
1y 7m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
1y 7m
Schedule
27 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-02-09
MISO-J2311 is a proposed wind generation project with a total capacity of 145 MW. The project is located in Lasalle County, Illinois, and is interconnected within the Midcontinent Independent System Operator (MISO) region, with Ameren Illinois as the utility. The project entered the MISO interconnection queue on October 18, 2024, with a proposed commercial operation date of February 9, 2024. Its interconnection status is currently in the Cluster Study phase.
The development project consists solely of wind generation, with 145 MW of wind turbine capacity. The point of interconnection (POI) is at Putnam. The project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
IL
County
Lasalle
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Putnam
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Paulding Putnam Hessen Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2311