MISO-J2312
47.9 MW generation in Putnam, IL · In queue since October 2024 · Proposed COD February 2024
47.9 MW
Capacity
1
Components
Wind
1y 7m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
1y 7m
Schedule
27 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-02-09
MISO-J2312 is a proposed wind generation project located in Putnam County, Illinois, within the Ameren Illinois service area. The project, with a total capacity of 47.9 MW, entered the MISO interconnection queue on October 18, 2024. Its proposed commercial operation date is February 9, 2024, and its interconnection status is currently in the Cluster Study phase.
The development project consists of 47.9 MW of wind generation capacity. It is listed in the MISO interconnection queue.
Generated from interconnection queue and public data sources
State
IL
County
Putnam
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Putnam
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Paulding Putnam Hessen Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.