MISO-J2316
77.5 MW generation in Dickinson, MI · In queue since September 2021 · Proposed COD September 2023
77.5 MW
Capacity
1
Components
Solar
4y 8m
In Queue
Cluster Study
IA Status
COD target: 2023
Total Duration
2 years
Schedule
32 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-09-15
MISO-J2316 is a proposed solar generation project with a total capacity of 77.5 MW, located in Dickinson County, Michigan. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on September 16, 2021. Its proposed commercial operation date is September 15, 2023. The point of interconnection is the Nordic 138kV Substation, and the project's interconnection status is currently in the Cluster Study phase.
The project is being managed within the American Transmission Company utility territory. It is currently listed as an active project within the MISO queue. Recent news coverage has discussed the development of solar projects in Michigan, including projects of this scale.
Generated from interconnection queue and public data sources
State
MI
County
Dickinson
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Nordic 138kV Substation
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Nordic Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2316