MISO-J2322
200 MW generation in Evangeline Parish, LA · In queue since May 2022 · Proposed COD July 2025
200 MW
Capacity
1
Components
Solar
4 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 2m
Schedule
10 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-07-02
MISO-J2322 is a proposed 200 MW solar generation project located in Evangeline Parish, Louisiana. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of May 17, 2022, and a proposed commercial operation date of July 2, 2025. The interconnecting utility is CLECO POWER.
The interconnection agreement (IA) status for MISO-J2322 is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Pine Prairie to Coughlin 138 kV line. The project is currently listed as active in the MISO queue.
Generated from interconnection queue and public data sources
State
LA
County
Evangeline Parish
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
CLECO POWER
Entity
MISO
Service Type
—
Point of Interconnection
Pine Prairie to Coughlin 138 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- HIGH
- POI Substation
- Pine
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2322