MISO-J2326
150 MW storage in Outagamie, WI · In queue since September 2022 · Proposed COD October 2025
150 MW
Capacity
1
Components
Battery
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 1m
Schedule
6 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-10-28
MISO-J2326 is a proposed 150 MW battery storage project located in Outagamie County, Wisconsin. The project, under review in the Midcontinent Independent System Operator (MISO) interconnection queue, entered the queue on September 13, 2022, with a proposed commercial operation date of October 28, 2025. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The project consists solely of battery storage, with a total capacity of 150 MW. The interconnecting utility is American Transmission Company, and the point of interconnection (POI) is the Werner West - Highway 22 345 kV substation.
Generated from interconnection queue and public data sources
State
WI
County
Outagamie
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Werner West - Highway 22 345 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Highway V
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2326