MISO-J2330
200 MW generation in Leflore, MS · In queue since September 2022 · Proposed COD October 2026
200 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-10-31
MISO-J2330 is a proposed 200 MW solar generation project located in Leflore County, Mississippi. The project, under consideration by Entergy Mississippi, LLC, entered the Midcontinent Independent System Operator (MISO) interconnection queue on September 15, 2022, with a proposed commercial operation date of October 31, 2026. Its interconnection agreement status is currently listed as "In Progress (unknown study)".
The proposed project consists of 200 MW of solar photovoltaic generation. The point of interconnection is the Winona to Greenwood 115 kV line. This development project is currently listed as active within the MISO queue.
Generated from interconnection queue and public data sources
State
MS
County
Leflore
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY MISSISSIPPI, LLC.
Entity
MISO
Service Type
—
Point of Interconnection
Winona to Greenwood 115 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2330