MISO-J2332
200 MW generation in Murray, MN · In queue since September 2022 · Proposed COD September 2027
200 MW
Capacity
1
Components
Wind
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2027
Total Duration
5 years
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-01
The proposed MISO-J2332 project is a 200 MW wind generation facility located in Murray County, Minnesota. The project, which is being developed within the Northern States Power Company service area, entered the Midcontinent Independent System Operator (MISO) interconnection queue on September 15, 2022. Its proposed commercial operation date is September 1, 2027.
The interconnection status for MISO-J2332 is currently in the Cluster Study phase. The point of interconnection (POI) is the Lyon County - Cedar Mountain 345kV substation.
Generated from interconnection queue and public data sources
State
MN
County
Murray
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
NORTHERN STATES POWER COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Lyon County - Cedar Mountain 345kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2332