MISO-J2343
130 MW storage in Marion, IN · In queue since September 2022 · Proposed COD May 2026
130 MW
Capacity
1
Components
Battery
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
3y 8m
Schedule
0 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-05-01
The proposed MISO-J2343 project is a 130 MW battery storage development in Marion County, Indiana. Interconnection to the grid is planned through the Georgetown - North 138.0kV point of interconnection. The project, listed in the MISO interconnection queue under Indianapolis Power & Light Company, entered the queue on September 14, 2022, with a proposed commercial operation date of May 1, 2026. Its interconnection status is currently in the Cluster Study phase.
The project consists entirely of battery storage, with a total capacity of 130 MW. It is listed as an active project within the MISO queue.
Generated from interconnection queue and public data sources
State
IN
County
Marion
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
INDIANAPOLIS POWER & LIGHT COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Georgetown - North 138.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.