MISO-J2350
115.5 MW generation in Pulaski, AR · In queue since September 2022 · Proposed COD September 2025
115.5 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3 years
Schedule
8 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-09-15
MISO-J2350 is a proposed solar generation project with a total capacity of 115.5 MW. The project is located in Pulaski County, Arkansas, and is being developed within the Entergy Arkansas service area. It entered the MISO interconnection queue on September 15, 2022, with a proposed commercial operation date of September 15, 2025.
The interconnection request, designated as MISO-J2350, is currently listed as "In Progress (unknown study)" for its Interconnection Agreement (IA) status. The point of interconnection (POI) is at the J2134 POI to White Bluff 115kV Line.
Generated from interconnection queue and public data sources
State
AR
County
Pulaski
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY ARKANSAS
Entity
MISO
Service Type
—
Point of Interconnection
J2134 POI to White Bluff 115kV Line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ARKANSAS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2350