MISO-J2353
278 MW generation in White, IN · In queue since September 2022 · Proposed COD May 2026
278 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
3y 8m
Schedule
0 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-05-01
MISO-J2353 is a proposed solar generation project with a total capacity of 278 MW. The project is located in White County, Indiana, and is being developed within the Northern Indiana Public Service Company (NIPSCO) service area. It entered the MISO interconnection queue on September 15, 2022, with a proposed commercial operation date of May 1, 2026.
The project's interconnection status is currently in the Cluster Study phase. The point of interconnection (POI) is the Reynolds - Burr Oak 345 kV Line.
Generated from interconnection queue and public data sources
State
IN
County
White
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
NORTHERN INDIANA PUBLIC SERVICE COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Reynolds - Burr Oak 345 kV Line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2353