250 MW generation in Morehouse Parish, LA · In queue since September 2022 · Proposed COD October 2026
250 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-10-31
MISO-J2371 is a proposed solar generation project located in Morehouse Parish, Louisiana, within the MISO region. The project, with a total capacity of 250 MW, is being developed within Entergy Louisiana's service territory. It consists of 250 MW of solar photovoltaic generation.
The project entered the MISO interconnection queue on September 14, 2022, with a proposed commercial operation date of October 31, 2026. Its interconnection agreement status is currently listed as "In Progress (unknown study)". The point of interconnection is the Dunn - Oak Ridge 115 kV line.
Generated from interconnection queue and public data sources
State
LA
County
Morehouse Parish
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY LOUISIANA
Entity
MISO
Service Type
—
Point of Interconnection
Dunn - Oak Ridge 115 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.