MISO-J2375
100 MW storage in Macon, IL · In queue since September 2022 · Proposed COD May 2027
100 MW
Capacity
1
Components
Battery
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2027
Total Duration
4y 8m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-05-07
MISO-J2375 is a proposed 100 MW battery storage project located in Macon County, Illinois. The project is in the MISO interconnection queue, having entered on September 15, 2022, with a proposed commercial operation date of May 7, 2027. The project's interconnection status is currently in the Cluster Study phase.
The project, which consists of a 100 MW battery, is being developed within the Ameren Transmission Company of Illinois service area. The point of interconnection is the Faraday substation. The project has appeared in recent news coverage regarding energy storage development in the region.
Generated from interconnection queue and public data sources
State
IL
County
Macon
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN TRANSMISSION COMPANY OF ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Faraday
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2375