MISO-J2382
115 MW hybrid in Randolph, MO · In queue since September 2022 · Proposed COD April 2026
115 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
3y 7m
Schedule
0 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-04-24
MISO-J2382 is a proposed 115 MW hybrid solar and battery project located in Randolph County, Missouri. The development project, consisting of 115 MW of solar generation, is in the MISO interconnection queue as of September 14, 2022. Ameren Missouri is the utility.
The project's proposed commercial operation date is April 24, 2026. Its interconnection status is currently in the Cluster Study phase, and the point of interconnection is the 5ADAIR - 5THMHIL (AECI) 161 kV line.
Generated from interconnection queue and public data sources
State
MO
County
Randolph
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN MISSOURI
Entity
MISO
Service Type
—
Point of Interconnection
5ADAIR - 5THMHIL (AECI) 161 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2382