MISO-J2384
125 MW generation in Shelby, IL · In queue since September 2022 · Proposed COD December 2024
125 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
2y 3m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-01
MISO-J2384 is a proposed solar generation project with a total capacity of 125 MW. The project is located in Shelby County, Illinois, within the Ameren Illinois service area. It entered the MISO interconnection queue on September 15, 2022, and has a proposed commercial operation date of December 1, 2024.
The project's interconnection status is currently in the Cluster Study phase. The point of interconnection is at the 4PANA-4SHELBYVL 138kV substation.
Generated from interconnection queue and public data sources
State
IL
County
Shelby
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
4PANA-4SHELBYVL 138kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2384