MISO-J2390
350 MW hybrid in Fulton, IL · In queue since September 2022 · Proposed COD September 2026
350 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
4 years
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-30
MISO-J2390 is a proposed 350 MW hybrid solar and battery project located in Fulton County, Illinois. The development project, consisting of 350 MW of solar generation, is in the MISO interconnection queue as of September 15, 2022, with a proposed commercial operation date of September 30, 2026. The project's interconnection point is at the Ipava 138kV substation, and its interconnection agreement status is currently in the Cluster Study phase.
The project is located within the Ameren Illinois utility service area.
Generated from interconnection queue and public data sources
State
IL
County
Fulton
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Ipava 138kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2390