MISO-J2396
400 MW generation in Calhoun, AR · In queue since September 2022 · Proposed COD May 2025
400 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
2y 8m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-05-31
MISO-J2396 is a proposed solar generation project with a total capacity of 400 MW, located in Calhoun County, Arkansas. The project is being developed within the Entergy Arkansas service area and interconnected to the MISO grid at the Sheridan EHV - El Dorado EHV 500 kV interconnection point.
The project entered the MISO interconnection queue on September 15, 2022, with a proposed commercial operation date of May 31, 2025. Its interconnection agreement status is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
AR
County
Calhoun
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY ARKANSAS
Entity
MISO
Service Type
—
Point of Interconnection
SHERIDAN EHV - EL DORADO EHV 500 kV (851.1)
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ARKANSAS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Sheridan
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2396