MISO-J2397
160 MW hybrid in Calhoun, AR · In queue since September 2022 · Proposed COD May 2025
160 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
2y 8m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-05-31
MISO-J2397 is a proposed 160 MW hybrid solar and battery project located in Calhoun County, Arkansas. The development project, which consists of 160 MW of solar generation, is in the Midcontinent Independent System Operator (MISO) interconnection queue. The project was entered into the queue on September 15, 2022, with a proposed commercial operation date of May 31, 2025.
The interconnection agreement (IA) status for MISO-J2397 is listed as "In Progress (unknown study)". The interconnecting utility is Entergy Arkansas. The point of interconnection (POI) is the Sheridan EHV - El Dorado EHV 500 kV line.
Generated from interconnection queue and public data sources
State
AR
County
Calhoun
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY ARKANSAS
Entity
MISO
Service Type
—
Point of Interconnection
SHERIDAN EHV - EL DORADO EHV 500 kV (851.1)
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ARKANSAS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Sheridan
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.