MISO-J2436
300 MW generation in Webster, IA · In queue since September 2022 · Proposed COD October 2030
300 MW
Capacity
1
Components
Wind
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2030
Total Duration
8y 1m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-10-01
The proposed MISO-J2436 project is a 300 MW wind generation facility located in Webster County, Iowa. The project, which is being developed by Cedar Falls Municipal Electric Utility, entered the MISO interconnection queue on September 12, 2022, with a proposed commercial operation date of October 1, 2030. Its point of interconnection is the Webster-Lehigh 345kV substation. The project's interconnection status is currently in the Cluster Study phase.
The development project consists of 300 MW of wind generation capacity. It is currently listed as an active project within the MISO interconnection queue.
Generated from interconnection queue and public data sources
State
IA
County
Webster
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
CEDAR FALLS MUNICIPAL ELECTRIC UTILITY
Entity
MISO
Service Type
—
Point of Interconnection
Webster-Lehigh 345kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2436