MISO-J2444
300 MW generation in Van Buren, MI · In queue since September 2022 · Proposed COD August 2026
300 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-08-01
MISO-J2444 is a proposed solar generation project located in Van Buren County, Michigan, with a total capacity of 300 MW. The development project, which consists entirely of solar photovoltaic generation, is in the Midcontinent Independent System Operator (MISO) interconnection queue. Its queue entry date is September 14, 2022, and the proposed commercial operation date is August 1, 2026. The project's interconnection agreement status is listed as "In Progress (unknown study)".
The proposed project is being developed within the Michigan Electric Transmission Company (METC) service area. The point of interconnection (POI) is the Argenta - Twin Branch 345kV line.
Generated from interconnection queue and public data sources
State
MI
County
Van Buren
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
Argenta - Twin Branch 345kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Branch
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2444